In February 2025, the Town of Apex acquired approximately 13 acres of land with the intention of developing a purpose‑built, vibrant mixed‑income, mixed‑tenure, and mixed‑use community.

What it is

Thirteen acres at the corner of South Hughes Street and Perry Road, bought by the Town in February 2025 to build something Apex has never built before.

The plan is a mixed-income, mixed-tenure community — rental apartments, attached and detached houses, and a small commercial building — held over the long term through the Community Land Trust that Council approved but had not yet used. Hughes Street is the first real application of it.

This project is intended to help address Apex’s need for affordable housing and is envisioned to explore a mix of pedestrian‑friendly housing types, including rental, single‑family attached, and single‑family detached homes. The site’s location near existing neighborhoods, services, and transit provides an opportunity to enhance connectivity and accessibility.

Planning is being done by Bolton & Menk under a $307,700 contract approved in December 2025 and paid from the Affordable Housing Fund. Three concept plans were presented to residents in August 2026. No developer has been selected, and the ownership structure has not been decided.

Three parcels, three zoning districts

The project is usually described as one 13.09-acre site. It is actually three adjoining parcels the Town bought together, each carrying a different zoning designation, and only one of them was still outside Town limits before August.

0 Perry Road

Acreage
0.67
Zoning
LI Light Industrial
Jurisdiction
Town limits

0 S Hughes Street

Acreage
7.15
Zoning
RA Residential Agricultural
Jurisdiction
Town limits*

*Annexed Aug 25, 2026

930 S Hughes Street

Acreage
5.28
Zoning
PUD-CZ Planned Unit Development
Jurisdiction
Town limits

The Three Concepts

Presented at the August 2026 input sessions. All three carry the same program — townhomes, apartments, a three-story commercial building, a stormwater pond and open space. They differ in arrangement and density, not in what gets built. None has been selected, and none has been submitted to the Town as an application.

Concept A

Frontage along Perry Rd

Townhomes and apartments line Perry Road, with the commercial building and the stormwater pond pushed toward the South Hughes Street side.

Concept B

Blocks around a central drive

Apartment blocks wrap the northern edge around a central drive, with the commercial building and pond to the south.

Concept C

Clustered, with perimeter green

A tighter cluster served by parking courts, commercial fronting Hughes Street, and open space held around the perimeter.

What’s there now?

The land is not empty

Planning documents describe the site as vacant. Residents describe it as a field their children have played on for years — youth football and lacrosse, in season, with informal use the rest of the year.

More than half of everything submitted to the Town’s comment map refers to the field, the sports played on it, or keeping the land open. It is the single most common subject in the public record for this project, ahead of traffic, transit, design and affordability combined.

“Keep Norris Park as a community field for sports! Kids love the Lacrosse and Pop Warner Football.”

-Public Comment Map

Timeline

Every entry below is tied to a meeting, a contract, or a recorded document. Dates are the date of the action, not the date it was reported.

February 7, 2025

The Town buys the site

Deed recorded at Book 19825, Page 1570. Recorded land sale price $3,213,400, against a January 2024 assessed value of $1,061,000. Purchased through the Affordable Housing Fund.

December 9, 2025

Council hires the planners

Contract CONT-2025-413 with Bolton & Menk, $307,700, approved on the consent agenda as item CN1. Scope runs from concept master plan through rezoning and a developer solicitation.

Apr – Jun, 2026

Online survey

First round of public input, collected through the Town’s PublicInput project page. An interactive comment map opened alongside it and remains live.

July 15, 2026

Neighborhood open house

Held at Stone Glen Apartments. 22 residents attended. The Town also counted this meeting toward the neighborhood meeting required before a rezoning application.

August 15 & 19, 2026

Three concepts presented

Community input sessions at the Apex Senior Center and the Halle Cultural Arts Center. Concepts A, B and C each showed townhomes, apartments, a three-story commercial building, a stormwater pond and surface parking.

August 25, 2026

Annexation approved, 5-0

Council held the public hearing on Annexation Petition No. 832 and approved it unanimously, bringing the land inside Town limits. The petition covered 7.995 acres — not the full 13.09-acre site — so the annexed area and the project area are not the same footprint.

Not scheduled

Rezoning

The land is zoned RA and cannot be developed as planned without a rezoning to a planned development district. The Town is both the applicant and the approving body. No hearing date has been set, and no application had been filed as of this update.

Expected

The town sequence

Once an application is filed, the contract anticipates a pre-application meeting, the Environmental Advisory Board, Parks and Recreation Advisory Board, Multimodal Transportation Advisory Board, four Technical Review Committee cycles, two neighborhood meetings, two Planning Board hearings and two Council hearings.

Expected

Developer solicitation

After rezoning, the Town intends to seek a development partner through a request for qualifications. No developer has been selected and the ownership structure remains undecided.

The Money

What has been spent so far

Two commitments to date: buying the land, and paying for the plan. Both came out of the Affordable Housing Fund. No construction money has been appropriated.

February, 2025

Land acquisition

$5,887,500

The Town bought all three parcels in a single transaction recorded at Deed Book 19825, Page 1570. Wake County’s record shows a land sale price of $3,213,400 against the center parcel, which is that parcel’s share rather than the whole purchase.

The excise stamps on the deed were $11,775. North Carolina charges $2 per $1,000 of consideration, which puts the full transaction at $5,887,500. That works out to $449,427 an acre across 13.10 acres — the identical per-acre rate implied by the $3,213,400 recorded against the center parcel’s 7.15 acres. The two figures describe the same deal at different scopes.

Note the center parcel’s assessed value in January 2024 was $1,061,000. The Town paid roughly three times assessed value for the parcel it later annexed. Assessed value is a tax figure and routinely trails market price, so a gap is expected — this one is larger than typical and the Town has not published an appraisal. Assessed values for the two outer parcels have not been checked.

Wake County Register of Deeds, D.B. 19825 PG. 1570 · excise stamps $11,775 · N.C.G.S. § 105-228.30

December, 2025

Planning and design

$307,700

Contract CONT-2025-413 with Bolton & Menk, approved on the consent agenda as item CN1. The scope runs from concept master plan through the rezoning application and into a developer solicitation. Three subconsultants sit under it: CommunityScale for the market study, Innovate P3 for delivery advisory and the developer RFQ, and an architectural firm carrying $58,500 of the total.

Town Council consent agenda, December 9, 2025, item CN1

Committed to date

Land and planning. Excludes staff time and any cost not carried on these two instruments.

$6,195,200

Contract CONT-2025-413 with Bolton & Menk, approved on the consent agenda as item CN1. The scope runs from concept master plan through the rezoning application and into a developer solicitation. Three subconsultants sit under it: CommunityScale for the market study, Innovate P3 for delivery advisory and the developer RFQ, and an architectural firm carrying $58,500 of the total.

Town Council consent agenda, December 9, 2025, item CN1

Public Input

What residents have said

The Town has run four rounds of engagement since April. What came back on its comment map does not line up neatly with the premise of the project.

The Town has run four rounds of engagement since April. What came back on its comment map does not line up neatly with the premise of the project.

Almost nobody who used the Town's comment map wants housing on this site.

Across 46 submissions — 15 map comments and 31 replies — 31 argue the land should stay open, be kept as playing fields, or that Apex should stop building. Those carry 187 of the 223 endorsements cast, 84 percent of all support registered.

Four submissions argue for the project. Between them they received one endorsement and eleven objections. Three of the four are the worst-received submissions on the map. The remaining eleven neither support nor oppose — they accept that something gets built and ask for sidewalks, buffering, traffic calming or reliable transit.

Residents repeatedly refer to the site as an existing park. Several name it Norris Park and describe it as the home of Pop Warner football and lacrosse. Whether that use is formal or informal, the land is not vacant in the way the planning materials imply.

This is not a poll. Anyone can submit and anyone can vote, votes are not verified, and 46 submissions are not a town of 86,000. What it shows is what the Town's own engagement tool collected, which is worth setting against how the results get summarized. Grouping submissions by position is our reading; every submission is reproduced below so you can check it.

“This property is already an important community space, used throughout the year by children, families, and neighbors for recreational sports and outdoor activities.”

-Public Comment Map

The Public Survey

Counts are of submissions, not of people. One person may have submitted more than once.

  1. Keep it open — 31 submissions

    The largest group by far. Preserve the fields for youth sports, keep the trees, make it a real park, or simply stop building. Several point out that this side of Apex has no nearby open green space while newer areas do.

  2. If it is built, connect it — 4 submissions

    Sidewalks and greenway access for the wider town, links to neighboring developments, and surface parking kept out of view from the street.

  3. Transit that can be relied on — 2 submissions

    A GoApex stop at Walmart, and a warning that housing marketed as transit-adjacent needs a durable commitment to keep the stops running.

  4. Build it — 4 submissions

    That most Apex workers cannot afford to live here, that apartments and townhomes are how entry-level wages get housed, and that preserving every vacant parcel as parkland has a tax cost. Collectively these drew one endorsement.

  5. Where it goes, not whether — 3 submissions

    Support for affordable housing paired with an objection to its placement — one asks why it lands on the older side of town rather than in Bella Casa and west Apex.

  6. Buffering, traffic and a correction — 3 submissions

    Perimeter planting for adjoining homes, traffic calming on the surrounding streets, and a note that the project map omits the Hopson Gateway PUD approved in December 2025 — 50 single-family homes, 170 townhomes and 400 apartments nearby, 20% of them affordable.

Every submission

All 46, ordered by endorsements, reproduced as submitted including typos. Names withheld. Filter by position to check the counts above for yourself — grouping submissions by stance is our reading, not a field in the Town's data.

  • This property is already an important community space, used throughout the year by children, families, and neighbors for recreational sports and outdoor activities. Rather than replacing it with more apartment buildings, I encourage the Town to preserve it as a public park or open recreational space.

    The surrounding neighborhoods have grown significantly in recent years, with many young families moving into the area. As our community continues to grow, so does the need for safe, accessible places where children can play and families can gather. Open space is becoming increasingly scarce, and once it is developed, it is rarely replaced.

    I encourage the Town to consider the long-term needs of our community by preserving this space for recreation and future generations.

    Community Preferences & Ideas ▲19 ▼1

  • Just leave a single open spot in apex. We need trees and we need land. It’s getting too hot due to all of the trees being cut down to build neighborhoods nobody can afford. Please just leave us something that isn’t being destroyed by new stuff

    Reply ▲15 ▼1

  • Leave this a green space or make it into an official park. Our area of town does not have a nearby green space that is open to everyone unlike other areas in Apex.

    Reply ▲14 ▼1

  • Leave it alone! Just because there is open space doesn't mean you have to build something! So many people use that field.

    Reply ▲13 ▼1

  • This property is already an important community space, used throughout the year by children, families, and neighbors for recreational sports and outdoor activities. Rather than replacing it with more apartment buildings, I encourage the Town to preserve it as a public park or open recreational space. The surrounding neighborhoods have grown significantly in recent years, with many young families moving into the area. As our community continues to grow, so does the need for safe, accessible places where children can play and families can gather. Open space is becoming increasingly scarce, and once it is developed, it is rarely replaced. I encourage the Town to consider the long-term needs of our community by preserving this space for recreation and future generations.

    Reply ▲13 ▼1

  • Keep Norris Park as a community field for sports! Kids love the Lacrosse and Pop Warner Football. Slow the growth Apex!!

    Reply ▲13 ▼1

  • Central Apex (ITP?) is getting more crowded with lots of infill being built. Open space is at a premium. This may be the last piece of park-worthy land inside the peakway.

    Known Issues & Challenges ▲12 ▼1

  • This last thing we need at this time, in Apex, is more housing. Please keep this space open for now.

    Reply ▲11 ▼1

How this section is built

Submissions come from the Town's own public comment map, published openly as part of the engagement process. Two sets are combined here: the 15 point comments and the 31 replies attached to them, which the map viewer shows as separate tables. The feed carries name and email fields. None appear here and none are stored — this page keeps only the text, the category and the vote counts.

The watch list

Questions we’re tracking

Should housing money pay for planning?

The $307,700 planning contract comes out of the Affordable Housing Fund. That is money raised to produce housing, spent on a plan rather than on units. It may well be the right use of it, and the eventual all-in public cost is the number that settles the question — but neither that figure nor the fund’s remaining balance has been published.

Was there an appraisal?

The purchase price and the excise stamps now reconcile: the Town paid about $5.89 million for all three parcels, $449,427 an acre. What remains open is the valuation behind it. The center parcel was assessed at $1.06 million and the Town paid roughly three times that. Assessed values trail the market, so a gap is expected — but no appraisal supporting the price has been released.

How would a nonprofit partnership be structured?

NC Newsline reported in March 2026 on arrangements in which for-profit developers partner with nonprofits in ways that carry property-tax consequences. Whether anything of that shape applies here depends entirely on a NeighborUp arrangement that does not yet exist. This is a question to ask when the structure is announced, not a claim about anyone’s intent.

Does the next round answer the open-space comments?